2-DAY SEMINAR:
"LET'S ANALYSE THE FIDIC CONTRACTS TOGETHER: CLAUSE BY
CLAUSE DISCUSSION OF THE MODEL CONTRACTS FOR CONSTRUCTION WORKS
AND SERVICES"
Saint Petersburg
1st-2nd November, 2010
The seminar is recommended to Employers, Developers, Engineers,
Contractors, Project Managers, Lawyers and Investors who have
interest in the matters of use of international model construction
contracts in the Russian context. The seminars offer the opportunity
to get familiarized with the main characteristics of such contracts
and to prepare for their practical application. The issues of
adaptation of the model contracts to specific projects are
discussed in the lectures and a number of cases are given.
The delegates will receive a printed course material and a CD with the seminar slides.
The Russian editions of the FIDIC model contracts, if necessary,
can be ordered before the seminars on our site
www.stpcp.pl.ru.
| Seminar daily duration: |
From 9.00 to 17.15 |
| The Venue: |
Business Centre "Mekhanobr",
3, 22nd line Vassilievsky Island, St. Petersburg,
Russia
Metro station "Vasileostrovskaya"
|
| Participation Fee: |
7788,00 roubles per participant.
Price includes: VAT, seminar material, coffee-break,
buffet lunch. |
| Discount: |
5% discount for the 2nd and further delegate from
the same organisation. |
| Recommended economy class hotel: |
Hotel "Azimut", 43/1, Lermontovsky
Prospect, St. Petersburg
Booking office: tel. (812) 740-2640,
spb@azimuthotels.ru
Attention! For delegates staying in the hotel
"Azimut" we will organise a transfer to
the seminar venue.
|
Information and payment details:
Tel.: (812) 449-65-02; (812)715-30-49; +7-921-763-9082.
Email: stpcp@peterlink.ru,
Internet: www.stpcp.pl.ru.
2-Day Seminar Programme:
"LET'S ANALYSE THE FIDIC CONTRACTS TOGETHER: CLAUSE BY
CLAUSE DISCUSSION OF THE MODEL CONTRACTS FOR CONSTRUCTION
WORKS AND SERVICES "
Saint Petersburg
1st-2nd November, 2010
| Time |
Topic |
| Day 1 |
The Construction Contract and the Plant,
Design and Build Contract |
| 8.30-8.55 |
Registration of Delegates |
| 9.00-10.30 |
Introduction to the FIDIC New Red Book and New Yellow Book:
- Documents constituting the Contract: Similarity and Differences
- Preamble and Appendices.
Clauses 1-3:
- General
- The Client: Power and Responsibility
- Authority and Functions of the Engineer
|
| 10.30-10.45 |
Interval |
| 10.45-11.30 |
Clauses 4-5:
- Contractor's Liability for Work Organisation
- Contractor's Liability foe Design.
|
| 11.30-12.00 |
Coffee-Break |
| 12.00-13.30 |
Clauses 6-11:
- Contractor's Personnel and Labour
- Material, Equipment and Quality of Works
- Contractual Time of Completion and Liquidated Damages
- Tests on Completion, Commissioning of Works and Defects Liability.
|
| 13.30-14.30 |
Lunch |
| 14.30-16.00 |
Clauses 12-16:
- Measurement and Evaluation
- Tests after Completion
- Variations and Price Adjustments
- Payment Method
- Termination of the Contract by Employer and by a Contractor.
|
| 16.00-16.15 |
Interval |
| 16.15-17.00 |
Clauses 17-20:
- Risks and Insurance
- Acts of God (force-majeure)
- Claims, Disputes and Arbitration.
|
| 17.00-17.15 |
Questions and Answers |
| Day 2 |
The EPC Contract, the Client/Consultant
Service Agreement and the newest Design Build & Operate
Contract |
| 9.00-10.30 |
Introduction to the FIDIC Silver Book (EPC Contract):
- FIDIC's Explanation of the EPC Contract Development
- Application of the EPC Contract
- Reasons to replace the Engineer's Function with the Employer's Representative
- EPC Pricing Method.
|
| 10.30-10.45 |
Interval |
| 10.45-11.30 |
Differences between the FIDIC Silver and New Yellow Books:
- Extent of Contractor's Responsibility
- Allocation of more Risks to Contractor
- Employer Control.
|
| 11.30-12.00 |
Coffee-Break |
| 12.00-13.30 |
Transformation of EPC to EPCM Contract:
- Comparison of EPC and EPCM Models
- EPC Contract Conditions to be altered for Transformation into EPCM.
A Case Study.
|
| 13.30-14.30 |
Lunch |
| 14.30-16.00 |
FIDIC White Book - Service Agreement:
- Types of Services this Agreement is intended for
- Document Structure
- General Conditions
- Necessary Appendices to the Agreement Conditions
that determine Contractual Subject, Time and Price.
|
| 16.00-16.15 |
Interval |
| 16.15-17.00 |
Presentation of the newest FIDIC Model Contract Conditions
for Design, Build and Operate:
- Overview
- Contents of General Conditions
- Comparison with the previous FIDIC Documents.
|
| 17.00-17.15 |
Questions and Answers |
|